IT Project & Priority list : Task Report

Task Start End Duration Completed Dependencies Total Cost Assigned Planned Start Start Variance Constraint Start Planned End End Variance Constraint End
1) IT Day to Day operations 2018-05-04, 8:00 AM 2018-06-07, 4:00 PM 5w 17% 2018-05-04, 8:00 AM 0h 2018-06-07, 4:00 PM 0h
1.1) Bank / Syspro inventory integration 2018-05-04, 8:00 AM 2018-05-08, 4:00 PM 3d 52% Shane D 2018-05-04, 8:00 AM 0h 2018-04-05, 8:00 AM 2018-05-08, 4:00 PM 0h
1.2) Data load (Scotts list) 2018-05-04, 8:00 AM 2018-05-07, 12:00 PM 1d 4h 54% Steve C 2018-05-04, 8:00 AM 0h 2018-05-04, 8:00 AM 2018-05-07, 12:00 PM 0h
1.3) SalesHabit Workflow Plugin app management 2018-05-07, 12:00 PM 2018-05-14, 12:00 PM 1w 0% 1.2 Steve C 2018-05-07, 12:00 PM 0h 2018-05-14, 12:00 PM 0h
1.4) Experlogix 4.0 BOM update 2018-05-04, 8:00 AM 2018-05-17, 4:00 PM 2w 0% Ross H 2018-05-04, 8:00 AM 0h 2018-05-17, 4:00 PM 0h
1.5) Cleanup of Dealer Leads that have been sent to the BANC 2018-05-04, 8:00 AM 2018-05-07, 4:00 PM 2d 0% Steve C 2018-05-04, 8:00 AM 0h 2018-05-07, 4:00 PM 0h
1.6) SalesHabit data cleanup and dealing with duplicates 2018-05-04, 8:00 AM 2018-05-07, 4:00 PM 2d 0% Jennifer H 2018-05-04, 8:00 AM 0h 2018-05-07, 4:00 PM 0h
1.7) Workflow, Plugin situation too many things firing 2018-05-08, 8:00 AM 2018-05-09, 4:00 PM 2d 0% 1.5 Steve C 2018-05-08, 8:00 AM 0h 2018-05-09, 4:00 PM 0h
1.8) Identifying a proper way to mark dealers as unique owners of campaigns 2018-05-04, 8:00 AM 2018-05-07, 4:00 PM 2d 0% Stephanie S 2018-05-04, 8:00 AM 0h 2018-05-07, 4:00 PM 0h
1.9) French language AE landing page 2018-05-04, 8:00 AM 2018-05-07, 4:00 PM 2d 30% Shane D 2018-05-04, 8:00 AM 0h 2018-05-07, 4:00 PM 0h
1.10) Tethys usage report feature for Stephen Reed 2018-05-09, 8:00 AM 2018-05-10, 4:00 PM 2d 100% 1.1 Shane D 2018-05-09, 8:00 AM 0h 2018-05-10, 4:00 PM 0h
1.11) Update all MSDS information for Stephen Reed 2018-05-11, 8:00 AM 2018-05-14, 4:00 PM 2d 0% 1.10 Shane D 2018-05-11, 8:00 AM 0h 2018-05-14, 4:00 PM 0h
1.12) Update French stores for Nanette Callens OK Implement BANC prospects "read receipts" feature for Natalie 2018-05-15, 8:00 AM 2018-05-17, 4:00 PM 3d 0% 1.11 Shane D 2018-05-15, 8:00 AM 0h 2018-05-17, 4:00 PM 0h
1.13) Set up redirects for expired quatro campaign links 2018-05-18, 8:00 AM 2018-05-24, 4:00 PM 1w 100% 1.12 Shane D 2018-05-18, 8:00 AM 0h 2018-05-24, 4:00 PM 0h
1.14) Move all source repositories to BitBucket and set up a proper development / deployment workflow for the dealer applications 2018-05-25, 8:00 AM 2018-05-31, 4:00 PM 1w 21% 1.13 Shane D 2018-05-25, 8:00 AM 0h 2018-05-31, 4:00 PM 0h
1.15) JIRA for IT projects 2018-06-01, 8:00 AM 2018-06-07, 4:00 PM 1w 25% 1.14 Shane D 2018-06-01, 8:00 AM 0h 2018-06-07, 4:00 PM 0h
1.16) New phone system rollout 2018-05-04, 8:00 AM 2018-05-08, 4:00 PM 3d 8% Ross H 2018-05-04, 8:00 AM 0h 2018-05-08, 4:00 PM 0h
1.17) Syspro EDI service error 2018-05-04, 8:00 AM 2018-05-07, 4:00 PM 2d 0% Ross H 2018-05-04, 8:00 AM 0h 2018-05-07, 4:00 PM 0h
1.18) Website server consolidation (GT.Net, RackSpace, Digital Ocean) 2018-05-04, 8:00 AM 2018-05-24, 4:00 PM 3w 0% Shane D 2018-05-04, 8:00 AM 0h 2018-05-24, 4:00 PM 0h
2) SalesHabit Project 2018-05-04, 8:00 AM 2018-06-14, 4:00 PM 6w 0% 2018-05-04, 8:00 AM 0h 2018-06-14, 4:00 PM 0h
2.1) Backend - Foundation setup 2018-05-04, 8:00 AM 2018-05-24, 4:00 PM 3w 0% 2018-05-04, 8:00 AM 0h 2018-05-24, 4:00 PM 0h
2.1.1) Finish installation of the portal platform on DEV & Prod 2018-05-04, 8:00 AM 2018-05-24, 4:00 PM 3w 0% Betach 2018-05-04, 8:00 AM 0h 2018-05-24, 4:00 PM 0h
2.2) Design interface 2018-05-25, 8:00 AM 2018-05-31, 4:00 PM 1w 0% 2018-05-25, 8:00 AM 0h 2018-05-31, 4:00 PM 0h
2.2.1) Wireframe Initial User Experience 2018-05-25, 8:00 AM 2018-05-31, 4:00 PM 1w 0% 2.1.1 Innovation Networks 2018-05-25, 8:00 AM 0h 2018-05-31, 4:00 PM 0h
2.3) Security 2018-06-01, 8:00 AM 2018-06-14, 4:00 PM 2w 0% 2018-06-01, 8:00 AM 0h 2018-06-14, 4:00 PM 0h
2.3.1) Creating a security structure for dealers 2018-06-01, 8:00 AM 2018-06-14, 4:00 PM 2w 0% 2.2.1 Stephanie S 2018-06-01, 8:00 AM 0h 2018-06-14, 4:00 PM 0h
3) Experlogix upgrade 2018-05-04, 8:00 AM 2018-05-24, 4:00 PM 3w 40% Ross H 2018-05-04, 8:00 AM 0h 2018-05-24, 4:00 PM 0h
4) Case Management Implementation 2018-05-04, 8:00 AM 2018-05-24, 4:00 PM 3w 0% Stephanie S 2018-05-04, 8:00 AM 0h 2018-05-24, 4:00 PM 0h
5) Upgrading to the latest version of CRM to fix existing bugs and give new capabilities to the marketing tea 2018-05-04, 8:00 AM 2018-06-14, 4:00 PM 6w 0% Steve C 2018-05-04, 8:00 AM 0h 2018-06-14, 4:00 PM 0h
6) Online backup automation DRP 2018-05-04, 8:00 AM 2018-05-31, 4:00 PM 4w 70% Ross H 2018-05-04, 8:00 AM 0h 2018-05-31, 4:00 PM 0h
7) Active directory update for all offices 2018-06-01, 8:00 AM 2018-06-14, 4:00 PM 2w 0% 6 Ross H 2018-06-01, 8:00 AM 0h 2018-06-14, 4:00 PM 0h
8) Syspro version 8 test upgrade evaluation 2018-05-15, 8:00 AM 2018-05-28, 4:00 PM 2w 0% 9 Ross H 2018-05-15, 8:00 AM 0h 2018-05-28, 4:00 PM 0h
9) Syspro invoice update and standardization 2018-05-08, 8:00 AM 2018-05-14, 4:00 PM 1w 0% 1.17 Ross H 2018-05-08, 8:00 AM 0h 2018-05-14, 4:00 PM 0h
10) Syspro Trade Promotion Module & training 2018-05-04, 8:00 AM 2018-05-31, 4:00 PM 4w 0% Syspro 2018-05-04, 8:00 AM 0h 2018-05-31, 4:00 PM 0h

Exported 2018-05-04